Saint Francis University

Athletics | News & Events | Visit Us! | Make A Gift | Looking Ahead    
Renewable Energy Center  
 

 Search Text: 

    
    
 
Left Corner   right corner
 
Donate Now!  Merchandise
 

 

Renewable Energy Center
Manor Drive
814-472-2872
renewable@francis.edu

Mailing Address
Saint Francis University
117 Evergreen Drive
P.O. Box 600
Loretto, PA 
15940-0600
Click for map

 

Sample Wind Energy Project

600kW Enertech E48 

600kW

$/kW

%

Turbine

Turbine and tower

$1,200,000

$2,000

Freight 

     200,000

     333

FAA lights

         3,600

         6

Subtotal

  1,403,600

  2,339

70.0%

Balance of Plant

Site Development

    150,000

     250

Foundations

      37,800

       63

Cranes plus labor

      38,400

       64

Electrical System & Transformer

      36,000

       60

Supervision

      11,400

       19

Subtotal

    273,600

     456

13.6%

Interconnection

HV line extension

      12,000

       20

Interconnection Feasibility Studies

        5,150

         9

Interconnection/Construction

      10,000

Labor (electrical) 

        7,200

       12

Subtotal

      34,350

       57

1.7%

Soft Costs

Legal

      18,000

       30

Permitting

      29,225

       49

Development/Engineering

    120,000

     200

Insurance (construction & transportation)

        9,000

       15

Title Insurance

        4,200 

         7

Financing (Application,
underwriting, loan fees)

         4,800

         8

Feasibility Study

       53,500

       89

MET Tower

       30,000

Contingencies

       24,000

       40

Subtotal

     292,725

     488

14.6%

Total

$2,004,275

 $3,340

Operating Costs

 

Operations & Maintenance

$     12,000

        20

Repair & Reserve

         7,800

        13

Management/Administrative

         6,000

        10

Property Taxes

         9,000

        15

Land Lease

         3,000

          5

Equipment Insurance

         6,000

        10

Miscellaneous

         3,600

          6

Total

$     47,400

        79

 

TURBINE

Turbine and tower: The estimates were obtained from various manufacturers. For any turbine where more than one quote was given, the amounts were averaged and the average was used.

Freight: The turbine, tower, and other components typically need to be shipped to the site. The quotes are from several turbine manufacturers. These estimates can vary greatly depending on the size of the turbine, number of turbines, and where the turbine is being shipped to and from.

FAA Lights: The lights are required by the FAA for any turbine over 200 feet tall. There are numerous companies which manufacture lights designed specifically for wind turbines. It was assumed for the 10.5 project with 5 turbines that at least 3 turbines would have lights installed on them. The cost of installing the lights is mixed in with the construction costs.

BALANCE OF PLANT

Site Development: The site development consists of geotechnical, surveying, turbine layout, and other site engineering work.

Foundations: The foundation is the base on which the turbines are erected.

Cranes plus Crane & Erection Labor: This line item is the cost for the rental of the cranes and labor associated with the construction process.

Electrical System & Transformer: This involves the process of hooking the electrical system (turbine wiring) to the transformer located at the power station which converts the power into energy.

Supervision: The cost associated with having the developer oversee the construction.

INTERCONNECTION

HV Line Extension: The line extension is when the turbine is interconnected either with transmission/distribution lines or a substation.

Interconnection Feasibility Studies: There is a flat rate for an application and an additional price per kilowatt fee for system impact studies.

Interconnection/Construction: This is to implement the necessary upgrades recommended by the system impact studies.

Labor (electrical): This line item consists of hiring electrical engineers and electricians to do the interconnection.

SOFT COSTS

Legal: Legal fees include title work and contracts. Additional fees may apply in areas without an adopted wind ordinance.

Permitting: Permitting includes Erosion and Sedimentation, wildlife impact studies, building permits, and National Pollutant Discharge Elimination System (NPDES) permits.

Development/Engineering: The development/engineering fees include fees for surveying, cut/fill, road construction, site clearing, and electrical engineering fees.

Insurance: This line item is for the insurance on the construction of the project.

Title Insurance: Title insurance protects the financiers of a project.

Financing: The financing line item is the cost associated with financing applications and associated legal fees.

MET Tower: The meteorological (MET) towers are installed to conduct feasibility studies for potential sites. The feasibility study helps to determine if a site has a developable wind resource.

Contingencies: Contingencies are the amount reserved for unforeseen costs which may arise during construction.

OPERATING COSTS

Operations and Maintenance: The monitoring and annual maintenance of turbines.

Repair and Reserve: The repair and reserve is money set aside typically based on a percentage of the original turbine cost. The money is used for any unexpected repairs necessary for the turbines.

Management/Administrative: The costs associated with the administrative duties required for a wind farm.

Property Tax: This was calculated by taking the appropriate tax rate and estimating the potential taxes for each project.

Land Lease: The land lease is the amount of money to be paid to the owner of the land.

Equipment Insurance: This line item covers the insurance on the equipment used in the operation and maintenance of the wind farm.

Miscellaneous: The miscellaneous line item is a fund of monies set aside for any unforeseen expenses that may arise.

 

Directions | Bookstore | Weather/Webcam | Site Map | SFU Home | ©2010 Saint Francis University